Milestone: V 0.3: The concept
Due:  November/December 2010

  • research into the originals.
  • extensively documenting the originals
  • making them temporary functional if possible.
  • creation of an emulated version of I/EYE.
  • comparison of characteristics of these versions.

Milestone: V 0.5: The Web
Due: February/March 2011.

  • creating a virtualized version of the emulated I/EYE
  • creating a Browser based emulated I/EYE
  • comparison of characteristics of these versions.
  • developing and documenting design time choices that will facilitate easier future emulation.

Milestone: V 0.8: The second
Due:  June 2011.

  • extensively documenting the original.
  • creating a virtualized emulated “time stretcher”.
  • creating a Browser based emulated “time stretcher”.
  • comparison of characteristics of these versions.
  • refining  design time choices that will facilitate easier future emulation.

Milestone: V 1: The final
Due: August 2011

  • The plans for the final presentation are still under development.